The Recycled Water Distribution System Expansion and Recycled Water Tertiary Treatment Plant (Project) Clean Water State Revolving Fund (CWSRF) No. C-06-5006-11

5 Documents in Project

Summary

SCH Number
2012031100
Lead Agency
El Toro Water District
Document Title
The Recycled Water Distribution System Expansion and Recycled Water Tertiary Treatment Plant (Project) Clean Water State Revolving Fund (CWSRF) No. C-06-5006-11
Document Type
NOD - Notice of Determination
Received
Posted
2/14/2013
Present Land Use
Local Street (City of Laguna Hills General Plan), no designation (City of Laguna Woods General Plan)
Document Description
The Recycled Water Distribution System Expansion: The Recycled Water Distribution System Expansion will include the construction of ~94,860 feet or 18 miles of recycled water pipelines beneath existing roadways. The pipelines will range from 4 to 16 inches, depending on the location. The pipelines will require excavations depths of 5 to 7 feet within the existing road right-of-way. The Recycled Water Tertiary Treatment Plant: The Recycled Water Tertiary Treatment Plant will include the construction of the new tertiary treatment facilities and a 5,000 - foot recycled water transmission pipeline.

Contact Information

Name
Ahmad Kashkoli
Agency Name
SWRCB - Div. of Financial Assist.
Contact Types
Lead/Public Agency

Location

Cities
Laguna Hills, Laguna Woods
Counties
Orange
Cross Streets
Ridge Route Drive and Moulton Parkway
Zip
92653
Total Acres
18
Parcel #
multiple
State Highways
I-5, 405; Hwy 133
Railways
No
Airports
No
Schools
San Joaquin ES
Waterways
No
Township
6
Range
8
Section
varies
Base
SBB&M

Notice of Determination

Approving Agency
State Water Board
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes