Fallbrook Public Utility District Wastewater Treatment Plant Rehabilitation

3 Documents in Project

Summary

SCH Number
2011102050
Lead Agency
Fallbrook Public Utility District
Document Title
Fallbrook Public Utility District Wastewater Treatment Plant Rehabilitation
Document Type
NOD - Notice of Determination
Received
Posted
8/6/2012
Present Land Use
A-70
Document Description
The Project will improve reliability and increase efficiency of the WWTP, and will provide better management of reclaimed water. The Project will involve: 1) constructing a new lift station, blower building, and an additional secondary clarifier; 2) installing new high efficiency blowers, dissolved oxygen controls, new reclamation filters, flow gauges, valves, controllers, internal mixed liquor recycled systems, baffles, mixers and dechlorination equipment; 3) rehabilitating the headworks and the operations center (lab, bathrooms and work areas); 4) removing a primary clarifier, and converting the primary clarifier into an emergency storage; 5) converting the existing overflow holding tank into an odor control facility; 6) rehabilitating and lining the equalization basin, including adding a diver wall in the equalization basin to separate and manage secondary and filtered effluents; 7) rehabilitating the existing reclamation facilities (flocculation and filtration); 8) installing an additional sludge dewatering centrifuge, and modifying the existing sludge dryer; 9) demolishing and existing pump station; 10) installing and modifying piping; and 11) upgrading the electrical system, and the supervisory control and data acquisition system.

Contact Information

Name
Lisa Lee
Agency Name
State Water Resources Control Board
Contact Types
Lead/Public Agency

Location

Cities
Fallbrook
Counties
San Diego
Cross Streets
Ammunition and Alturas
Zip
92028
Total Acres
8.62
Parcel #
104-190-17, 104-190-04
Airports
Fallbrook Airpark
Schools
4
Waterways
Fallbrook Creek
Township
9S
Range
4W
Section
25
Base
SBB&M

Notice of Determination

Approving Agency
State Water Board
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.