Allied Gardens Improv 1

23 Documents in Project

Summary

SCH Number
2011091045
Lead Agency
City of San Diego
Document Title
Allied Gardens Improv 1
Document Type
NOD - Notice of Determination
Received
Posted
6/22/2023
Document Description
PROJECT DESCRIPTION: The project is for the replacement of approximately 13,900 Lineal Feet (LF) of existing water mains with new 8, 12, and 16-inch PVC water mains, including associated water services and fire hydrants. An existing pressure reducing station will be abandoned in place and a new underground pressure reducing station will be built. Construction also consists of the following: replacement of approximately 9,600 LF of existing 8-inch sewer mains with new 8-inch PVC sewer mains, abandonment of approximately 500 LF of existing 8-inch sewer mains, along with associated sewer laterals, and manholes. The project also consists of associate curb ramps, street slurry seal, street resurfacing and traffic control plans. Open trenching will occur within the paved right of way and within city easements on private property

Contact Information

Name
Jeffrey Szymanski
Agency Name
City of San Diego
Job Title
Senior Planner
Contact Types
Lead/Public Agency

Location

Cities
San Diego
Counties
San Diego
Regions
Citywide, Countywide
Other Information
Replacement of approximately 13,900 Lineal Feet

Notice of Determination

Approving Agency
City of San Diego
Approving Agency Role
Lead Agency
Approved On
County Clerk
San Diego
Final Environmental Document Available at
Development Services Department, 1222 First Avenue, San Diego, CA 92101

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
Yes (An Addendum to Environmental Impact Report)
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.

Download CSV New Search Print