City of Palo Alto Recycled Water Project
5 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2011062037
- Lead Agency
- City of Palo Alto
- Document Title
- City of Palo Alto Recycled Water Project
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 10/1/2015
- Present Land Use
- Various
- Document Description
- The City of Palo Alto proposes the expansion of the regional recycled water system to deliver recycled water produced by the City's Regional Water Quality Control Plant (RWQCP) to customers in the City, potentially including Alta Mesa Memorial Park, Stanford Research Park, and others. The proposed project includes about 10 miles of pipeline (backbone, lateral, and connecting pipelines) and two pump stations (one at the RWQCP and another at Mayfield Soccer Fields, along the pipeline alignment). The project would initially provide approximately 900 acre feet per year of recycled water for irrigation.
- Contact Information
-
Karin North
City of Palo Alto
Lead/Public Agency
2501 Embarcadero Way
Palo Alto, CA 94301
Phone : (650) 329-2104
Location
- Coordinates
- 37°25'22"N 122°08'33"W
- Cities
- Palo Alto
- Counties
- Santa Clara
- Cross Streets
- E. Meadow Dr.'; Cowper St; El Dorado Ave; Alma St; Page Mill Road; Hanover St; Hillview Ave
- Zip
- 94301
- State Highways
- Hwy 101
- Railways
- Caltrain along Alma Ave
- Airports
- Palo Alto Airport
- Schools
- Multiple
- Waterways
- SF Bay, Adobe Creek, Barron Creek, Matadero Creek
Notice of Determination
- Approving Agency
- City of Palo Alto
- Approving Agency Role
- Lead Agency
- Approved On
- Final Environmental Document Available at
- 250 Hamilton Avenue, 5th Floor, Palo Alto, CA 94301
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- No
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.