Dingee Backbone Pipeline Replacement Project

2 Documents in Project

Summary

SCH Number
2011032031
Lead Agency
East Bay Municipal Utility District (EBMUD)
Document Title
Dingee Backbone Pipeline Replacement Project
Document Type
NOD - Notice of Determination
Received
Posted
5/12/2011
Present Land Use
Land Use designated as single family; General Plan designated as low density, Detached Unit and Hillside Residential
Document Description
The project consists of installing approximately 3-1/2 miles of aging potable water pipeline. A 12,000-foot segment of the Dingee Backbone Pipeline, a primary transmission pipeline that provides water to 18,000 customers located in the Central Oakland Hills, will be replaced in Golden Gate Avenue, Broadway Terrace, Proctor Avenue, and Harbord Drive. A portion of the backbone pipeline will also be relocated to avoid the Hayward Fault zone and a potential earthquake-induced landslide area. Up to 7,100 feet of small diameter distribution pipeline will also be replaced in Contra Costa Road, Roble Road, Proctor Avenue and Agnes Street. The smaller distribution pipelines need to be installed in order to maintain customer service once the existing backbone pipeline is removed from service.

Contact Information

Name
Tim Fuette
Agency Name
East Bay Municipal Utility District
Contact Types
Lead/Public Agency

Location

Cities
Berkeley, Oakland
Counties
Alameda
Cross Streets
Golden Gate Ave to Broadway Terrace to Proctor Ave to Julia St. to Harbord Dr.
State Highways
Hwy 13, 24
Schools
Oakland Unified
Waterways
Lake Temsecal, Temescal Creek

Notice of Determination

Approving Agency
East Bay Municipal Water District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print