Watkins Gate Well and Pipeline Project

3 Documents in Project

Summary

SCH Number
2011031082
Lead Agency
Marina Coast Water District
Document Title
Watkins Gate Well and Pipeline Project
Document Type
NOD - Notice of Determination
Received
Posted
12/17/2012
Present Land Use
The project site is located within the former Fort Ord, which was previously a U.S. Army base. Future development has been planned for the former Fort Ord base as part of the Fort Ord Reuse Plan, adopted in 1997 by the Fort Ord Reuse Authority (FORA). The proposed well site and associated water conveyance pipeline is located within an area designated for planned development as a mixed use district in the FORA Plan.
Document Description
The California Department of Public Health (Department), as the Responsible Agency, will be issuing a water supply permit to operate. The proposed project is to construct a water supply well to provide to Marina Coast Water District's (MCWD) existing water supply distribution system; a well house to enclose the well; an electrical building to enclose motor controls, mechanical and electrical appurtenances; a backup emergency power generator; and an associated distribution pipeline. The well would connect to an existing 24-inch water line connection with the installation of 2,500 feet of a new water conveyance pipeline to be located within the paved roadway of Watkins Gate Road in the East Garrison area of MCWD's Ord community service area. A test well will be installed and monitored prior to the construction of the well. If the test well is determined operational, the well will be made a permanent monitoring well.

Contact Information

Name
Jan Sweigert
Agency Name
CA Department of Public Health
Contact Types
Lead/Public Agency

Location

Cities
Marina
Counties
Monterey
Cross Streets
Watkins Gate Road / Reservation Road
Zip
93933
Total Acres
~1
Parcel #
031011031000
Waterways
Salinas River

Notice of Determination

Approving Agency
Calfiornia Department of Public Health
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print