Sharpe Grading Permit

3 Documents in Project

Summary

SCH Number
2010101033
Lead Agency
San Luis Obispo County
Document Title
Sharpe Grading Permit
Document Type
NOD - Notice of Determination
Received

Document Description
Request by Michael Sharpe for a grading permit to authorize unpermitted ("as built") grading, The as-built grading is proposed to accommodate a future single family residence (approximately 7,151 square feet) and detached garage (approximately 1,342 square feet). Additionally, the unpermitted site work included extension of a 16-foot driveway extending from the existing driveway to the building pad; creation of a new 12-foot driveway extending from Huasna Townsite Road to the building pad; and disposal of spoils material in an previously disturbed area containing ornamental vegetation. In total, approximately 12,000 cubic yards of cut and 12,000 cubic yards of fill occurred over an approximately 6.0 acre portion of a 95 acre parcel. Also to be considered under this environmental document are as-built construction permits for a deck of approximately 2,184 square feet, two pedestrian bridges, and a vehicular bridge, all of which involved site work within the channel of Huasna Creek. The proposed project is within the Agricultural land use category.

Contact Information
Michael Conger
San Luis Obispo County
County Government Center, Room 30
San Luis Obispo, CA 93408-2040

(805) 781-5600

Location

Coordinates
35°5'37.35"N 120°22'43.85"W
Cities
Arroyo Grande
Counties
San Luis Obispo
Cross Streets
Huasna Townsite Road/Ciervo Trail
Zip
93420
Total Acres
95.31
Parcel #
085-012-032
Schools
Lucia Mar USD
Waterways
Huasna Creek

Notice of Determination

Approving Agency
Planning Department of the County of San Luis Obispo
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
Department of Planning and Building, County of San Luis Obispo County Government Center, Room 200 San Luis Obispo, Ca 93408-2040

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
Yes