Fresno-Clovis Southern Water Intertie Project-Leonard Avenue, Ashlan Avenue to the Gould Canal
3 Documents in Project
Summary
SCH Number
2010061010
Lead Agency
City of Clovis
Document Title
Fresno-Clovis Southern Water Intertie Project-Leonard Avenue, Ashlan Avenue to the Gould Canal
Document Type
NOD - Notice of Determination
Received
Posted
11/22/2010
Present Land Use
Public street right of way
Document Description
The City of Clovis proposes to install underground pipe 16 inch in diameter, to connect the public water system of the City of Fresno with the public water system of the City of Clovis. The Project consists of installing the pipeline beneath existing public roads, beginning at the intersection of Ashlan Avenue and Leonard Avenue, proceeding south along Leonard Avenue. The line proceeds on the west side of the roadway ~2,900 ft south of Ashlan Avenue (paralleling Dog Creek) to a water valve station at the south side of the Gould Canal and connects to the existing Fesno system on the south side of the Gould Canal. The Project will occur partially in the City of Clovis and partially in Fresno County, but entirely within the Clovis Sphere of Influence.
The Project also includes the installation of an underground pipe, 12 inches in diameter, to provide the City of Fresno the use of recycled water. The pipe would be installed beneath the east side of Leonard Avenue beginning at the intersection of Ashlan Avenue and Leonard Avenue proceeding south and end at the south side of the Gould Canal. The City of Fresno will provide future connection.
Contact Information
Name
Ryan Burnett
Agency Name
City of Clovis
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Clovis
Counties
Fresno
Cross Streets
Ashlan and Leonard Ave
State Highways
SR 168, 180
Schools
Clovis Unified-Reagan
Waterways
Dog Creek
Township
21
Range
24
Section
13
Notice of Determination
Approving Agency
City of Clovis
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.