California State University, California State Polytechnic University, San Luis Obispo, Pennington Creek Bridge Removal and Streambed Restoration Project.

3 Documents in Project

Summary

SCH Number
2010051033
Lead Agency
California State Polytechnic University, San Luis Obispo
Document Title
California State University, California State Polytechnic University, San Luis Obispo, Pennington Creek Bridge Removal and Streambed Restoration Project.
Document Type
NOD - Notice of Determination
Received

Document Description
The Pennington Creek Bridge Removal and Streambed Restoration project would entail the removal of the wooden bridge over Pennington Creek, and restoration of instream habitat areas following completion of the removal effort. The project is proposed to occur during the late summer/early fall of 2010, to meet low flow permit requirements, and to avoid the nesting bird season. The project site is not within the Coastal Zone, and will not require a Coastal Development Permit. Bridge removal will require permit authorization from the US Army Corps of Engineers (USACE), Regional Water Quality Control Board (RWQCB), and California Department of Fish and Game (CDFG) for work within the channel, and for dewatering and diversion activities.

Contact Information
Joel Neel
California State Polytechnic University, San Luis Obispo
1 Grand Avenue
San Luis Obispo, CA 93407

805-756-2193

Location

Coordinates
35°35'14.9"N 120°'20.2"W
Cities
San Luis Obispo
Counties
San Luis Obispo
Cross Streets
Pennington Creek Rd, Watson Dr
Zip
93407
Total Acres
1
Parcel #
73-221-021, 007
State Highways
Hwy 1
Schools
Cuesta College
Waterways
Pennington Creek
Township
30S
Range
12E
Section
Chorro
Base
MDB&M

Notice of Determination

Approving Agency
Trustees
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
California Polytechnic State University 1 Grand Avenue, Building 70 San Luis Obispo, CA 90802-4210

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A Statement of Overriding Considerations was adopted for this project
N/A
(5) Findings were made pursuant to the provisions of CEQA
Yes
Download CSV New Search