Crown Cove Dock Project
3 Documents in Project
Summary
SCH Number
2010011063
Lead Agency
California Department of State Parks, Division of Boating and Waterways
Document Title
Crown Cove Dock Project
Document Type
NOD - Notice of Determination
Received
Posted
5/16/2011
Present Land Use
Crown Cove Aquatic Center
Z: State Parks
GP: City of Coronado Civic Use and Open Space
Document Description
The proposed Project involves the construction of a new recreational dock at the Crown Cove Aquatic Center. A concrete sidewalk would be constructed to extend from the existing paved driveway area, which would slope down to a concrete abutment connecting to an accessible 8-foot wide gangway. The gangway would extend approximately 100 feet and would connect to a 20-foot by 30-foot long fiberglass floating platform held in place with two concrete piles driven into the bay floor. The dock would be accessible to the general public; however, the main purpose of the dock is to support educational programs offered at the aquatic center. Construction of the dock will allow the Crown Cove Aquatic Center to expand its curriculum and to provide instruction to a greater number of students.
Contact Information
Name
Anna Buzaitis
Agency Name
San Diego Unified Port District
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Coronado
Counties
San Diego
Cross Streets
SR 75/North of Coronado Bay Rd
Zip
92118
Total Acres
<1
Parcel #
SR 75
State Highways
SR 75
Schools
Silver Strand ES, Silver Strand ES (US Naval Base)
Waterways
San Diego Bay, Pacific Ocean
Base
SBB&M
Notice of Determination
Approving Agency
San Diego Unified Port District
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.