San Diego Shipyard Sediment Remediation Project - North Shipyard (for Project Modifications)

9 Documents in Project

Summary

SCH Number
2009111098
Lead Agency
Regional Water Quality Control Board, Region 9
Document Title
San Diego Shipyard Sediment Remediation Project - North Shipyard (for Project Modifications)
Document Type
NOD - Notice of Determination
Received
Posted
7/9/2014
Present Land Use
Industrial/San Diego Unified Port District
Document Description
The Project Modifications to the originally-approved remediation project will include the following: (1) installation of a permanent sheetpile bulkhead wall; (2) removal of a submerged sheetpile wall and marine railway debris from the bay bottom; (3) removal of the existing approximately 5,140-square-foot Pier 2 structure from BAE Systems' leasehold; (4) elimination of on-site dredge handling by transferring sediment from barge or scow directly to trucks; and, (5 increasing the total permitted dredge volume from 90,800 to 105,800 cubic yards.

Contact Information

Name
Mayra Medel
Agency Name
San Diego Unified Port District
Contact Types
Lead/Public Agency

Location

Cities
San Diego
Counties
San Diego
Cross Streets
West of Sampson Street & Harbor Drive
Zip
92113
Total Acres
17.5
State Highways
I-5
Railways
SD&AE RR, BNSF RR
Airports
San Diego International
Schools
Perkins Elementary
Waterways
San Diego Bay
Township
17S
Range
3W
Base
SBB&M

Notice of Determination

Approving Agency
San Diego Unified Port District
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print