San Diego Shipyard Environmental Restoration Fund - NASSCO (South)

9 Documents in Project

Summary

SCH Number
2009111098
Lead Agency
Regional Water Quality Control Board, Region 9
Document Title
San Diego Shipyard Environmental Restoration Fund - NASSCO (South)
Document Type
NOD - Notice of Determination
Received
Posted
7/19/2013
Present Land Use
Industrial/San Diego Unified Port District
Document Description
Modification of the Shipyard Sediment Remediation Project to approve a 15,000 cubic yard increase in the dredge volume and the use of a different sediment management area for dewatering and stockpiling of dredged sediment at the S-Lane parcel within the NASSCO shipyard leasehold. The previously certified Final Program Environmental Impact Report evaluated Project details and activities including sediment dredging in identified dredge areas adjacent to NASSCO and BAE Systems shipyards in San Diego Bay; the dewatering and solidfication of dredged material; the potential treatment of decanted water and transport of the removed sediment to an appropriate landfill for disposal.

Contact Information

Name
David Barker
Agency Name
San Diego Unified Port District
Contact Types
Lead/Public Agency

Location

Cities
San Diego
Counties
San Diego
Cross Streets
West of Sampson Street & Harbor Drive
Zip
92113
Total Acres
17.5
State Highways
I-5
Railways
SD&AE RR, BNSF RR
Airports
San Diego International
Schools
Perkins Elementary
Waterways
San Diego Bay
Township
17S
Range
3W
Base
SBB&M

Notice of Determination

Approving Agency
California Regional Water Quality Control Board, San Diego
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print