Clean Water State Revolving Fund (CWSRF) No. C-06-4841-110,-120,-130, and -140
7 Documents in Project
Summary
SCH Number
2009082066
Lead Agency
City of Vacaville
Document Title
Clean Water State Revolving Fund (CWSRF) No. C-06-4841-110,-120,-130, and -140
Document Type
NOD - Notice of Determination
Received
Posted
6/24/2011
Document Description
The project will improve the Plant's treated water quality effluent but will not increase the Plant's treatment capacity. The project includes: 1) upgrading the secondary treatment system to meet the effluent ammonia and nitrate limitations, 2) increasing wet weather flow handling capability to reduce the blending of primary and secondary effluent during peak storm events, and 3) installing a filtration system so that combined filtrated and disinfected effluent will meet Title 22 of the California Code of Regulations in the months of May through October each year. To implement the improvements and upgrades within the compliance deadlines, the Project will bid as four separate segments. Each project segments will have its own financing agreement.
Contact Information
Name
Michelle Lobo
Agency Name
SWRCB - Division of Financial Assistance
Contact Types
Lead/Public Agency
Phone
Location
Counties
Solano
Cross Streets
Vaca Station Road, Fry Road and Lewis Road (6040 Vaca Station Road)
Zip
95625
Total Acres
~115
Parcel #
142-110-050, -040; 142-200-040
State Highways
Sr 113, US 80
Railways
UPRR
Airports
Nut Tree, Travis AFB
Schools
Sierra School of Solano Co, Jean Callison ES
Waterways
Old Alamo Creek
Township
6N
Range
1E
Section
30
Base
MDB&M
Other Location Info
City/Nearest Community: Elmira
Notice of Determination
Approving Agency
SWRCB - Div. Financial Assist.
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes