Eldorado-Ivanpah Transmission Project

6 Documents in Project

Summary

SCH Number
2009071091
Lead Agency
California Public Utilities Commission (CPUC)
Document Title
Eldorado-Ivanpah Transmission Project
Document Type
NOD - Notice of Determination
Received
Posted
11/9/2011
Present Land Use
BLM utility corridor; Open Space; Energy
Document Description
The proposed project involves construction of a 220/115-Kkilovolt (kV) Ivanpah Substation, the replacement of approximately 35 miles of existing 115-kV line with a double-circuit 220-kV, transmission line between the existing Eldorado Substation and the Ivanpah Dry Lake area, and installation of a telecommunication system along two separate and redundant pathways. The Project will result in impacts to 51.73 acres of desert tortoise (Gopherus agassizii) habitat including temporary impacts to 45.5 acres and permanent removal of 6.23 acres. The Project is expected to result in incidental take of desert tortoise, which is designated as a threatened species under the California Endangered Species Act (CESA). The incidental take permit referenced above as issued by DFG authorizes incidental take of species listed under CESA that may occur as a result of project implementation.

Contact Information

Name
Kimberly Nicol
Agency Name
DFG, Inland Desert Region
Contact Types
Lead/Public Agency

Location

Counties
San Bernardino
Zip
92364
Total Acres
35 miles
State Highways
I-15; Hwy 95
Railways
UPRR
Airports
Proposed SNSA
Schools
No
Waterways
Ivanpah Dry Lake/Roach Dry Lake
Township
multi
Range
multi
Section
multi
Other Location Info
City/Nearest Community: Nipton, CA Primm, NV

Notice of Determination

Approving Agency
DFG
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes