Owens Lake Revised Moat and Row Dust Control Measures Supplemental EIR

8 Documents in Project

Summary

SCH Number
2008121074
Lead Agency
City of Los Angeles
Document Title
Owens Lake Revised Moat and Row Dust Control Measures Supplemental EIR
Document Type
NOD - Notice of Determination
Received
Posted
2/2/2012
Document Description
Construct, install, operate, monitor and maintain 3.5 square miles of moat and row dust control measures. A moat and row element is composed of a berm (row) 5-feet high with 1.5 to 1 sloping sides and a base 19 feet wide, an access road on both sides of the row up to 15 feet wide, flanked on either side by ditches (moats) 4 to 5.5 feet deep and up to 20 feet wide. The moat and row elements will be oriented perpendicular with the primary and secondary wind directions and serve as wind breaks. A portion of the rows will have a five foot high sand fence placed on top of them. Moat and row elements will disturb up to 33 percent of the 3.5 square miles. The State Lands Commission action is the amendment of Lease No. PRC 8079.9, a General Lease - Public Agency Use, to include the placement of above-grade sprinkler systems in the Sand Fence Area T1A-1.

Contact Information

Name
Drew Simpkin
Agency Name
California State Lands Commission
Contact Types
Lead/Public Agency

Location

Counties
Inyo
Cross Streets
State Route 395, HIghway 136, Highway 190
Zip
93545
Total Acres
2,240
State Highways
395, 136, 190
Railways
UPRR
Airports
none
Schools
none
Waterways
Los Angeles Aqueduct, Owens River
Other Location Info
City/Nearest Community: Lone Pine

Notice of Determination

Approving Agency
California State Lands Commission
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.