California Polytechnic State University San Luis Obispo, Recreation Center Expansion, Schematic Plan Approval

2 Documents in Project

Summary

SCH Number
2008111033
Lead Agency
California State Polytechnic University, San Luis Obispo
Document Title
California Polytechnic State University San Luis Obispo, Recreation Center Expansion, Schematic Plan Approval
Document Type
NOD - Notice of Determination
Received

Document Description
The project will construct an addition of 95,014 GSF to the existing Recreation center, which will have 64,199 GSF remaining after demolishing 27,360 GSF, for a total new gross square footage of 159,213. In addition, to the existing four-court gym, the project will add a lobby, a two-court gym, a multi-activity court, a weight/fitness area, exercise room, wellness center, an indoor jogging track, a leisure pool and administrative offices. This project will also renovate the existing locker rooms and swimming pool mechanical spaces as well as incorporate a new roof and updated HVAC equipment. The new portion of the building will align with the existing buildings on the north, east and south sides.

Contact Information
Robert Kitamura
Trustees of the California State University
401 Golden Shore
Long Beach, CA 90802-4120

805-756-2581

Location

Coordinates
35°17'"N 120°39'58"W
Cities
San Luis Obispo
Counties
San Luis Obispo
Cross Streets
S. Perimeter Dr.
Zip
93407
Total Acres
1.5
State Highways
1
Railways
UPRR
Waterways
Stenner Creek

Notice of Determination

Approving Agency
Trustees
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
CA Polytechnic State University Facilities Planning 1 Grand Avenue, Building 70, RM 27 San Luis Obispo, CA 93407 CSU Chancellor's Office Capital Planning, Design and Construction 401 Golden Shore Long Beach, CA 90802-4210

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
No
(5) Findings were made pursuant to the provisions of CEQA
Yes
Download CSV New Search