Ridgemark Wastewater Treatment and Recycled Water Improvements Project

5 Documents in Project

Summary

SCH Number
2008071031
Lead Agency
Sunnyslope County Water District
Document Title
Ridgemark Wastewater Treatment and Recycled Water Improvements Project
Document Type
NOD - Notice of Determination
Received

Document Description
The Project will consolidate and upgrade the RM I and RM II facilities. The new facilities include headworks, sequencing batch reactor, and solids handling facilities at the RM I site. Effluent from sequencing batch reactor will be pumped to the existing percolation ponds at the RM I site for disposal. Waste activated sludge from the sequencing batch reactor will be pumped to the biosolids storage basin on a daily basis. The biosolids will be continually aerated in the storage basin then pumped to adjacent covered solids drying beds for dewatering during dry weather periods. Dried solid will be hauled to a landfill for disposal. A new operations building will also be built on RM I site for system control, operation, and maintenance needs. An emergency diesel generator will be installed outside the operations building. Also, a pump station and a conveyance pipeline will be built at the RM II site to convey raw wastewater from the RM II facility to the RM I facility. The existing RM I and RM II treatment ponds will be decommissioned.

Contact Information
Michelle Lobo
State Water Resources Control Board
Division of Financial Assistant 1001 I Street 16th Floor
Sacramento, CA 95814

(916) 341-6983

Location

Coordinates
36°48'42"N 121°22'41"W
Cities
Hollister
Counties
San Benito
Cross Streets
Airline Highway and Ridgemark Drive
Zip
95023
State Highways
25
Railways
UPRR
Schools
Southside, Cerra Vista
Waterways
San Benito River
Township
13S
Range
5E/6E
Base
MDB&M

Notice of Determination

Approving Agency
State Water Resources Control Board
Approving Agency Role
Responsible Agency
Approved On
Final EIR Available Location
State Water Board, Division of FInancial Assistance 1001 I Street, 16th Floor Sacramento, CA 95814

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
Yes
(5) Findings were made pursuant to the provisions of CEQA
Yes
Download CSV New Search