East-West Water Transmission Pipeline Project- Phase II
3 Documents in Project
Summary
SCH Number
2008012059
Lead Agency
City of Fairfield
Document Title
East-West Water Transmission Pipeline Project- Phase II
Document Type
NOD - Notice of Determination
Received
Posted
4/8/2008
Present Land Use
Public rights of way. Major Arterial, Minor Arterial, Collector, and Residential Medium Density, Light Industrial and Business Park and Public Facility in Fairfield. In Solano County, Agriculture.
Document Description
The project is part of the City of Fairfield East-West Water Transmission Pipeline Project, a 36" water transmission line connecting existing water mains. The purpose of the new transmission main is to pump water from the North Bay Regional Water Plan to Cordelia providing a redundant system for the existing waterline. Construction of the pipeline under-crossing below Ledgewood Creek will require the excavation of jacking and receiving pits on either side of the channel. The eastern jacking pit will be ~12' wide by 40' long and ~10' from below the flow line of Ledgewood Creek to the pipeline invert.
Contact Information
Name
Anna Holmes
Agency Name
California Dept. of Fish and Game
Contact Types
Lead/Public Agency
Address
Phone
Location
Cities
Fairfield
Counties
Solano
Cross Streets
Hale Ranch Road/Cordelia Road and West America Drive and Adagio Drive
Zip
94533, 34
State Highways
SR-12, I-80
Railways
UPRR, Redwood Northern RR
Schools
Solano Community College
Waterways
Ledgewood Creek, Suisun Valley Creek and Dan Wilson Creek
Notice of Determination
Approving Agency
CDFG
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.