Corralitos Creek Fisheries Enhancement Project

3 Documents in Project

Summary

SCH Number
2007122007
Lead Agency
Watsonville, City of (City of Watsonville)
Document Title
Corralitos Creek Fisheries Enhancement Project
Document Type
NOD - Notice of Determination
Received
Posted
9/26/2008
Present Land Use
Rural residential land use in a Residential-Agricultural General Plan Designation

Document Description
The City of Watsonville proposes to build a new 120-foot V-section pool and weir type fish passage ladder on the right bank of Corralitos Creek adjacent to the existing fish ladder with parallel ladders side by side to accommodate juvenile and adult fish passage. The existing fish ladder facility wil be filled and covered with concrete. The right bank steel wall which supports the existing structure will be removed and replaced with a new concrete wall. Log weirs downstream of the existing fish passage strucure will be removed and replaced with 5 rock weirs. The City also porposes to remove the intake structure surrounding the screened intake pipes and build a new one.

Contact Information
Suzanne DeLeon
Department of Fish and Game
Bay Delta Region P.O. Box 47
Yountville, CA 94599

Phone : (831) 440-9433

Location

Counties
Santa Cruz
Cross Streets
Eureka Canyon Road and Las Colinas
Zip
95076
Total Acres
0.236
Parcel #
107-031-61 and 107-031-6
Township
11S
Range
1E
Other Location Info
City/Nearest Community: Corralitos

Notice of Determination

Approving Agency
Department of Fish and Game
Approving Agency Role
Responsible Agency
Approved On
Final Environmental Document Available at
Santa Cruz County 701 Ocean Street Santa Cruz, CA 95065

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A