Las Encinas Hospital 2007 Master Development Plan

3 Documents in Project

Summary

SCH Number
2007071094
Lead Agency
City of Pasadena
Document Title
Las Encinas Hospital 2007 Master Development Plan
Document Type
NOD - Notice of Determination
Received
Posted
9/24/2009
Document Description
In anticipation of the needs of the City of Pasadena and surrounding communities, the 2007 master Development PLan seeks to augment existing senior services by increasing assisted living beds from the current 9 beds to a total of 81 beds and increasing independent living units from 85 existing to 230 total units. The proposes project would provide expanded medical (psychiatric) office space from the existing 15 units (14,174 sf) to 31 total offic units (an additional 45,407 sf). In addition, a new psychiatrict hospital would be constructed to consolidate psychiatric patient care in a single, secure facility affording greater security to the neighborhood and modern facilities for staff and patient care. The new psychiatrict hospital woul also consolidate adolescent care facilities. Residential treatment programs and chemical dependency would be consolidated from the 68 existing beds located in 6 different buildings to accommodate 38 beds in a single facility (Gables Building 7), a reduction of 30 beds. adolescent psychiatry would be consolidated into a single building accommodating. 28 beds in the central portion of the campus south of the existing hospital building. Approximately 15 existing buildings are proposed to be removed.

Contact Information

Name
Scott Reimers
Agency Name
City of Pasadena
Contact Types
Lead/Public Agency

Location

Cities
Pasadena
Counties
Los Angeles
Cross Streets
2900 East Del Mar Boulevard
Zip
91109
Total Acres
24.7
State Highways
SR 110, I-210
Railways
Gold Line light rail

Notice of Determination

Approving Agency
City of Pasadena
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.