San Joaquin Pipeline No. 4 - Eastern Segment (California Endangered Species Act (CESA) Incidental Take Permit No. 2081-2011-061-03 (ITP) Minor Amendment No. 1)

10 Documents in Project

Summary

SCH Number
2007032138
Lead Agency
City and County of San Francisco
Document Title
San Joaquin Pipeline No. 4 - Eastern Segment (California Endangered Species Act (CESA) Incidental Take Permit No. 2081-2011-061-03 (ITP) Minor Amendment No. 1)
Document Type
NOD - Notice of Determination
Received
Posted
7/7/2015
Document Description
This proposed project involves construction of one new pipeline segment, approximately 6.5 miles with ancillary components including construction of a new valve house, site improvements at Oakdale Portal, a tie-in vault, construction of a throttling station, and upgrades to valves at Cashman Creek. Construction will use existing access roads, creation of an access road and a spur road, widen two cattle guards, temporary stockpiling of soils, and three temporary construction easement (TCE) staging areas within the ROW and two TCE staging areas outside of the Joaquin Pipeline System right-of-way. The Project will result in permanent impacts to 0.74 acres of California tiger salamander grassland refugia habitat, and 107.89 acres of temporary and semi-permanent impacts to CTS refugia habitat. The Project is expected to result in incidental take of CTS, which is designated as a threatened species under CESA. The ITP referenced above as issued by CDFW authorizes incidental take of species listed under CESA that may occur as a result of Project implementation. Minor Amendment No. 1 extends the expiration date of the ITP and modifies the Project Description to include the additional covered activities at Cashman Creek consisting of replacing 65 feet of 56-inch diameter corroded pipeline along the SJPL No. 1 and the replacement of the concrete blow-off housing box. The Amendment does not increase the temporary, semi-permanent, or permanent upland refugia habitat impacts as contemplated in the ITP and will result in no additional impacts to CTS.

Contact Information

Name
Annee Ferranti
Agency Name
CDFW
Contact Types
Lead/Public Agency

Location

Cities
Oakdale
Counties
San Joaquin, Stanislaus, Tuolumne
Cross Streets
various
Zip
various
Parcel #
Various
State Highways
I-5, I-580, SR 132, SR 33
Railways
UPRR, Sierra
Waterways
various

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.