City of Hollister Sprayfield Project and San Benito County Regional Recycled Water Facility Project
11 Documents in Project
Summary
SCH Number
2007021136
Lead Agency
San Benito County Water District
Document Title
City of Hollister Sprayfield Project and San Benito County Regional Recycled Water Facility Project
Document Type
NOD - Notice of Determination
Received
Posted
6/27/2014
Document Description
The proposed project would result in the use of recycled water (RW) treated at the City of Hollister's (COH) Domestic Wastewater Treatment Plant (DWTP) for agricultural irrigation on currently irrigated lands located along Wright Road adjacent to the RW distribution pipeline that extends to the COH Municipal Airport. Under the project, RW would offset groundwater use for agricultural irrigation for approximately 1,900 acres of currently irrigated lands within unincorporated San Benito County, just west of the COH. Construction activities would include installation of RW service lines and minor pipeline turn-outs on said existing RW pipeline extending from the DWTP to the Airport.
Contact Information
Name
Jeff Cattaneo
Agency Name
San Benito County Water District
Contact Types
Lead/Public Agency
Phone
Location
Cities
Hollister
Counties
San Benito
Cross Streets
State Route 156, State Route 25 and Wright Road
Zip
95023
Parcel #
various
State Highways
156
Railways
Southern Pacific
Airports
Hollister Municipal
Schools
Calaveras Elementary School
Waterways
San Benito River
Township
12,13S
Range
4, 5E
Section
Unsect
Base
MDB&M
Notice of Determination
Approving Agency
San Benito County Water District
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.