Bay Division Pipeline Reliability Upgrade, Lower Crystal Springs Dam Improvement, Crystal Springs/ San Andreas Transmission System Upgrade

14 Documents in Project

Summary

SCH Number
2007012002
Lead Agency
City and County of San Francisco
Document Title
Bay Division Pipeline Reliability Upgrade, Lower Crystal Springs Dam Improvement, Crystal Springs/ San Andreas Transmission System Upgrade
Document Type
NOD - Notice of Determination
Received
Posted
9/20/2011
Document Description
In connection with approval of the project identified above, the SFPUC required compensatory habitat mitigation to address biological resources impacts that would result from implementation of the projects. Three habitat compensation sites, known as Homestead Pond, San Andreas Reservoir Wetlands, and Adobe Gulch Grasslands which are located within S.F. Peninsula Watershed lands that are owned by the City and County of San Francisco but managed by the SFPUC, will provide mitigation for certain of these impacts: On September 13, 2011, the SFPUC adopted Resolution No. 11-0156, authorizing the General Manager of the SFPUC to negotiate and enter into Water System Improvement Program (WSIP) funded Contract No. WD-2641R, Habitat Reserve Program, Homestead pond, San Andreas Reservoir Wetlands, and Adobo Gulch Grasslands, and upon successful negotiations, approve the plans and specifications for these three habitat compensation sites and award the contract.

Contact Information

Name
Timothy Johnston
Agency Name
San Francisco Planning Department
Contact Types
Lead/Public Agency

Location

Cities
Hillsborough
Counties
San Mateo
Cross Streets
Skyline Boulevard and Crystal Springs Road
Zip
various
Parcel #
Various
State Highways
92, 35, I-280
Schools
Odyssey Middle School, Highlands Elem.
Waterways
San Mateo, Laguna, San Andreas, and Pilarcitos Creeks
Other Information
Lat/Long Cont. 37-29-2.976/122-19-8.724

Notice of Determination

Approving Agency
SF Planning Department
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print