Lower Crystal Springs Dam Improvement Project [California Endangered Species Act (CESA) Incidental Take Permit No. 2081-2011-049-03 (ITP)]

14 Documents in Project

Summary

SCH Number
2007012002
Lead Agency
City and County of San Francisco
Document Title
Lower Crystal Springs Dam Improvement Project [California Endangered Species Act (CESA) Incidental Take Permit No. 2081-2011-049-03 (ITP)]
Document Type
NOD - Notice of Determination
Received
Posted
11/18/2014
Document Description
This proposed project is the operation of the Crystal Springs Reservoir and the creation, enhancement and restoration of Crystal Springs fountain thistle and Marin western flax habitat. The San Francisco Public Utilities Commission will perform maintenance, enhancement and expansion activities in existing areas of fountain thistle and Marin western flax subpopulations, as well as pursue the establishment or re-establishment of additional subpopulations. The Project will result in impacts to approximately 20,000 fountain thistle (Cirsium fontinale var. fontinale) plants and approximately 800 Marin western flax (Hesperolinon congestum) plants. The project is expected to result in incidental take fountain thistle, which is designated as an endangered species under CESA and the incidental take of Marin western flax which is designated as a threatened species under CESA. The ITP referenced above as issued by CDFW authorizes incidental take of species listed under CESA that may occur as a result of Project implementation.

Contact Information

Name
Annee Ferranti
Agency Name
CDFW Bay Delta Region
Contact Types
Lead/Public Agency

Location

Cities
Hillsborough
Counties
San Mateo
Cross Streets
Skyline Boulevard and Crystal Springs Road
Zip
various
Parcel #
Various
State Highways
92, 35, I-280
Schools
Odyssey Middle School, Highlands Elem.
Waterways
San Mateo, Laguna, San Andreas, and Pilarcitos Creeks
Other Information
Lat/Long Cont. 37-29-2.976/122-19-8.724

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.