Brooktrails Lake Emily Dam
3 Documents in Project
Summary
SCH Number
2006102081
Lead Agency
Brooktrails Community Services District
Document Title
Brooktrails Lake Emily Dam
Document Type
NOD - Notice of Determination
Received
Posted
6/25/2007
Present Land Use
Lake Emily - water supply / Public Facilities-Airport and Brooktrails Township combining district / Public Facilities
Document Description
The proposed project involves installation of an inflatable gateway and dam reinforcement at the spillway of an existing dam at Lake Emily on Dutch Henry Creek and Willits Creek, tributary to Mill Creek, tributary to Outlet Creek, tributary to the Eel River in Mendocino County. Installation of the inflatable spillway will increase the maximum water level of Lake Emily by three feet to accommodate original volumes. Water supplies water to the Brooktrails Township Community Services District (BTCSD) via a water treatment facility at Lake Ada Rose. The California Department of Fish and Game is executing a Lake and Streambed Alteration Agreement number 1600-2006-0822-3 pursuant to Section 1602 of the Fish and Game Code to the project applicant, Mr. Mike Chapman, BTCSD.
Contact Information
Name
Corinne Gray
Agency Name
California Department of Fish and Game
Contact Types
Lead/Public Agency
Phone
Location
Cities
Willits
Counties
Mendocino
Cross Streets
Primrose Drive, Blue Jay Lane
Zip
95490
Total Acres
19
Parcel #
N/A; LAT/LONG: 39.4467/123.3914
State Highways
101
Airports
Ells Field Airport
Waterways
Willits Creek, Dutch Henry Creek, Lake Emily, Lake Ada Rose
Township
18N
Range
14W
Section
2, 3
Other Location Info
City/Nearest Community: Brooktrails Township
Notice of Determination
Approving Agency
California Department of Fish and Game
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.