Lake March Bypass Pipeline

2 Documents in Project

Summary

SCH Number
2006101146
Lead Agency
Western Municipal Water District
Document Title
Lake March Bypass Pipeline
Document Type
NOD - Notice of Determination
Received
Posted
4/20/2007
Present Land Use
Roadway / Rural Residential / Public Facilities and Open-Space Recreational
Document Description
The Lake March Bypass Pipeline alignment consists of 1,024 linear feet of 16-diameter pipeline. THe pipeline will be installed utilizing traditional trenching techniques and will occur within the existing roadway. Since the 1950's , Lake March has provided non-potable water service and storage for the Riverside National Cementary and the Genera. Old Golf Course. Service to the Riverside National Cemetery, the General Olf Golf Course, and Air Force Willage West hsa been interrupted due to the limited storage capacity of Lake March and the time required by the Distirct to receive, transfer, and distribute water through it.

Contact Information

Name
Thomas Safford
Agency Name
Western Municipal Water District
Contact Types
Lead/Public Agency

Location

Cities
Moreno Valley, Perris, Riverside
Counties
Riverside
Cross Streets
Nandina Avenue and Clark Street
Zip
92518
Total Acres
~ 1,000 lin. ft.
Parcel #
295-270-008
State Highways
I-215
Railways
BNSF
Airports
March Air Reserve Base
Schools
Mead Valley ES, Tomas Rivera MS, Manuel L. Reed ES
Township
3S
Range
4W
Section
34
Base
SBBM
Other Location Info
City/Nearest Community: Woodcrest, Glen Valley

Notice of Determination

Approving Agency
Western Municipal Water District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No