Department of Water Resources Water Right Petitions to Add a Point of Re-diversion to Serve the Grizzly Ranch Development

5 Documents in Project

Summary

SCH Number
2006052096
Lead Agency
Plumas County
Document Title
Department of Water Resources Water Right Petitions to Add a Point of Re-diversion to Serve the Grizzly Ranch Development
Document Type
NOD - Notice of Determination
Received
Posted
3/3/2008
Present Land Use
Prime Recreation
Document Description
The Department of Water Resources (DWR) has petitioned for a point of re-diversion for water released from Grizzly Valley Dam (Lake Davis) under Permits 15254 and 15255 (Applications 16950 and 21443). Water will be re-diverted by Plumas County Flood Control and Water Conservation District (Plumas County) for the Grizzly Ranch Development. The water diversion pipe will have a fish screen and metering station. The metered flow will be continuously recorded and will not exceed the additional volume being discharged from the dam. The water will be pumped to a large pond within the development and used for golf course irrigation.

Contact Information

Name
James Kassel
Agency Name
State Water Resources Control Board
Contact Types
Lead/Public Agency

Location

Cities
Portola
Counties
Plumas
Cross Streets
Grizzly Road, Hwy. 70
Parcel #
025-100-032
Waterways
Grizzly Creek
Township
23N
Range
14E
Section
20

Notice of Determination

Approving Agency
State Water Resources Control Board
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print