Sanger Wastewater Treatment Plant
3 Documents in Project
Summary
SCH Number
2006051135
Lead Agency
City of Sanger
Document Title
Sanger Wastewater Treatment Plant
Document Type
EIR - Draft EIR
Received
Present Land Use
Public Facility and Recreation, School, and Conservation / Public Facility
Document Description
The project consists of the adoption of the proposed "Waste Water Treatment Master Plan" for the City of Sanger's Wastewater Treatment Plant (WWTP) and the associated upgrade and expansion and operation of the facility through the year 2035. The project site is located about 1.5 miles southeast of the center of the City of Sanger (City) and west of the Kings River.
New improvements include the following: construction of a headworks to replace the existing domestic headworks, a parshall flume for influent flow metering, two mechanical bar screens, two aerated grit chambers, an anoxic basin, an influent pump station, an oxidation ditch and associated facilities, two 55-foot diameter secondary clarifiers, a Return Activated Sludge (RAS) pump station disinfection facilities including a duplicate of the existing tank and metering pumps, a chlorine contact basin, and a second centrifuge. In addition, new support facilities include: Control/Administration Building, expansion of maintenance building, a new standby generator, upgrade of existing electrical system, and Supervisory Control and Data Acquisition (SCADA) workstations through the plant. Two of the existing effluent pumps would be replaced with larger pumps. A second domestic force main (18-inch diameter) to transport treated effluent to the Lincoln Ponds will be constructed parallel to the existing force main. The route for the second pipeline will be 4 miles long and is within the right-of-way for Newmark Avenue. A second electrical transmission line may also be necessary and will run parallel with the existing transmission line along Ross and North Avenues.
The proposed project would expand the WWTP to treat an Average Day Maximum Month Flow (ADMMF) of 5.3 million gallons per day (mgd).
Contact Information
Name
John A. White
Agency Name
City of Sanger
Contact Types
Lead/Public Agency
Phone
Location
Cities
Sanger
Counties
Fresno
Cross Streets
South of the intersection of East North and South Ross Avenue
Zip
93657
Total Acres
7
Schools
Jefferson Elementary and Lincoln Elementary
Waterways
Kings River
Township
14S
Range
22E
Section
25
Base
MDB&M
Notice of Completion
State Review Period Start
State Review Period End
State Reviewing Agencies
California Department of Fish and Wildlife, Central Region 4 (CDFW), California Department of Parks and Recreation, California Department of Transportation, District 6 (DOT), California Highway Patrol, California Regional Water Quality Control Board, Central Valley Fresno Region 5 (RWQCB), Department of Toxic Substances Control, Department of Water Resources, Resources Agency, Resources, Recycling and Recovery, California Native American Heritage Commission (NAHC), State Water Resources Control Board, Divison of Financial Assistance
State Reviewing Agency Comments
California Native American Heritage Commission (NAHC), State Water Resources Control Board, Divison of Financial Assistance
Development Types
Waste Treatment:Other (Wastewater Treatment Plant expansion)
Local Actions
Master Plan
Project Issues
Aesthetics, Agriculture and Forestry Resources, Air Quality, Cultural Resources, Cumulative Effects, Drainage/Absorption, Flood Plain/Flooding, Geology/Soils, Growth Inducement, Hazards & Hazardous Materials, Hydrology/Water Quality, Land Use/Planning, Mineral Resources, Noise, Population/Housing, Public Services, Recreation, Schools/Universities, Septic System, Sewer Capacity, Solid Waste, Transportation, Vegetation, Wetland/Riparian, Wildfire, Wildlife
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.