French Camp Slough Sewer Pipeline

9 Documents in Project

Summary

SCH Number
2005122101
Lead Agency
City of Stockton
Document Title
French Camp Slough Sewer Pipeline
Document Type
NOD - Notice of Determination
Received
Posted
7/6/2021
Document Description
The Project is limited to the construction of a sewer pipeline that would run under the French Camp Slough by means of jack and bore. The jacking and receiving pits would both be excavated to a depth of approximately 26 feet for the new sewer line to run approximately 10 feet below the thalweg of French Camp Slough. Both pits will be approximately 100 feet away from the top-of-bank and any riparian vegetation. A reinforced concrete pipe of 442 linear feet in length with two steel casing pipes of 0.5 inch minimum thickness and 343 linear feet in length will be installed.

Contact Information

Name
Ian Ralston
Agency Name
Department of Fish and Wildlife
Contact Types
Responsible Agency

Location

Counties
San Joaquin
Regions
Northern California
Township
01S
Range
07E
Section
6
Base
MDM
Other Location Info
The project is located on French Camp Slough adjacent to where it crosses South Airport Way.

Notice of Determination

Approving Agency
California Department of Fish and Wildlife
Approving Agency Role
Responsible Agency
Approved On
County Clerk
San Joaquin
Final Environmental Document Available at
the office location listed above for the Lead Agency. CDFW’s record of execution of the above Lake and Streambed Alteration Agreement as Responsible Agency is available at CDFW’s regional office.

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
No
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Notice of Determination

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.

Download CSV New Search Print