Borup Culvert Installation Project, Agreement No. 2008-0077-R4
2 Documents in Project
Summary
SCH Number
2005122057
Lead Agency
Tuolumne County
Document Title
Borup Culvert Installation Project, Agreement No. 2008-0077-R4
Document Type
NOD - Notice of Determination
Received
Posted
8/4/2008
Present Land Use
Vacant
Z: A-20 (General Agricultural, 20 acre minimum) under Title 17 of the Tuolumne County Ordinance code
GP: Rural Residential (RR)
Document Description
The California Department of Fish and Game is executing a Lake and Streambed Alteration Agreement pursuant to Section 1602 of the Fish and Game Code to the project applicant, Laureen Borup, for the Culvert Installation Project. The applicant proposes to install seven, corrugated metal pipe (CMP) culverts, of diameters ranging from 18 to 60 inches, in unnamed tributaries to Garrotte Creek. Also proposed is the installation of rock rip-rap slope protection around culvert inlets and outfalls, and seeding and mulching of disturbed areas.
Contact Information
Name
Brian Erlandsen
Agency Name
California Department of Fish and Game
Contact Types
Lead/Public Agency
Phone
Location
Counties
Tuolumne
Cross Streets
Old Highway 120 / SR-120
Total Acres
117.2 +/-
Parcel #
66-181-73
State Highways
120
Airports
Pine Mountain Lk
Schools
Tenaya / Tioga
Waterways
Tributary to Garrotte Creek
Township
1S
Range
16E
Section
27, 28
Base
MD
Other Location Info
City/Nearest Community: Groveland
Notice of Determination
Approving Agency
California Department of Fish and Game
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.