Calaveras Dam Replacement Project

14 Documents in Project

Summary

SCH Number
2005102102
Lead Agency
San Francisco, City and County of (City and County of San Francisco)
Document Title
Calaveras Dam Replacement Project
Document Type
NOD - Notice of Determination
Received

Document Description
The proposed project is the Calaveras Dam Replacement Project, referred to as the "CDRP Variant," located in unincorporated areas of Alameda and Santa Clara Counties on lands owned by the City and County of San Francisco. The purpose of the project is to improve the seismic and water delivery reliability of Calaveras Reservoir and to restore its historical storage capacity. The project consists of the following: construction of a new dam to replace the existing Calaveras Dam at the north end of the existing Calaveras Reservoir; replacement or modification of related facilities such as the spillway, intake shaft and adits, outlet pipe, stream discharge valves, and instrumentation; construction of fishery enhancements at Calaveras Dam and at the Alameda Creek Diversion Dam (ACDD), including fish screens at both dams and a fish ladder at the ACDD; upgrade of an existing electrical distribution line to serve construction needs; long-term implementation of instream flow releases from both dams for fisheries and other aquatic resources; and long-term implementation of an Adaptive Management Implementation Plan for central CA coast steelhead. Project construction will include use of disposal and borrow areas north and south of Calaveras Reservoir and will require approximately 4 years, beginning in 2011 with targeted completion in 2015.

Contact Information
Chris Kern
City and County of San Francisco
1650 Mission Street, Suite 400
San Francisco, CA 94103-2479

415-575-9037

Location

Coordinates
37°29'"N 121°49'"W
Cities
Milpitas Fremont
Counties
Santa Clara Alameda
Cross Streets
Calaveras Creek in the Diablo Mountain Range
Zip
94586
Total Acres
1960 ac
Parcel #
096-0100-027-00
Waterways
Calveras & Alameda Creeks
Township
05S
Range
01E
Section
13

Notice of Determination

Approving Agency
City and County of San Francisco
Approving Agency Role
Lead Agency
Approved On
Final EIR Available Location
N/A

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A Statement of Overriding Considerations was adopted for this project
Yes
(5) Findings were made pursuant to the provisions of CEQA
Yes