Southeast Water Reliability Project (Montebello Loop)

2 Documents in Project

Summary

SCH Number
2005031175
Lead Agency
Central Basin Municipal Water District
Document Title
Southeast Water Reliability Project (Montebello Loop)
Document Type
NOD - Notice of Determination
Received
Posted
5/3/2005
Present Land Use
Project is entirely within the road rights-of-way that pass by a variety of residential, commercial, recreational, institutional, and light industrial uses. The pipeline would be constructed where various utility lines currently exist, and with adequate horizontal and vertical separation to ensure public health safety. GP: Open Space and Park, roads right-of-way Z: roads right-of-way, Open Space and Park
Document Description
The proposed project is a local recycled water distribution system that would offset the imported potable water supplies from the State Water Project. The Project would ultimately serve 28 potential public and private entity sites along the pipeline, including one anchor customer (Montebello Golf Course) at the terminal end of the pipeline, with over 800 acre feet per year of recycled water. The project would include the installation of approximately 4.5 miles of 30-inch recycled water pipeline that would be buried within roadway in the Cities of Pico Rivera and Montebello. The starting point of the pipeline would be in the City of Pico Rivera at the intersection of San Gabriel River Parkway and Beverly Boulevard, where the proposed pipeline would connect to the existing San Gabriel River Parkway Recycled Water Pipeline Lateral. From this starting point, the pipeline would be routed west along Beverly Boulevard throughout the City of Pico Rivera and enter the City of Montebello. At the intersection of Beverly Boulevard and Rea Drive in the City of Montebello, the pipeline would be routed north along Rea Drive to Lincoln Avenue. The pipeline would then be routed west along Lincoln Avenue and end at the Montebello Golf Course. The trench excavated for the installation of the new pipeline would average eight feet in depth and four feet in width. The trench would be refilled using native backfill with an asphalt cap.

Contact Information

Name
Uzi Daniel
Agency Name
Central Basin Municipal Water District
Contact Types
Lead/Public Agency

Location

Cities
Montebello, Pico Rivera
Counties
Los Angeles
Cross Streets
Beverly Blvd. / Rosemead Blvd. / Lincoln Ave.
Zip
90660, 40
State Highways
60, 19
Railways
UPRR
Schools
North Park MS, Pio Pico, La Merced and Wilcox ES, Schurr HS
Waterways
San Gabriel River, Rio Hondo Channel
Township
2S
Range
12W
Base
SBBM

Notice of Determination

Approving Agency
Board of Directors of the Central Basin Municipal Water District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.