Rohnert Park Sewer Interceptor / Outfall Project
2 Documents in Project
Summary
SCH Number
2004122125
Lead Agency
City of Rohnert Park
Document Title
Rohnert Park Sewer Interceptor / Outfall Project
Document Type
NOD - Notice of Determination
Received
Posted
2/11/2005
Present Land Use
Diverse Agriculture with the following combining districts: Floodway, Floodplain, Community Separator, Second Unit Exclusion, Rural Residential, Agricultural and Residential, Public Institutional.
Document Description
The project consists of the construction 3.5 miles of a buried 30-inch interceptor pipeline and its outfall at the regional wastewater treatment plant. The new pipeline will lie primarily in local roadways beginning from the City of Rohnert Park's Sewer Pump Station on Redwood Drive and terminating at the Santa Rosa Subregional Water Reclamation Facility (Laguna Plant) on Llano Road. The City has initiated the Sewer Interceptor / Outfall Project to increase reliability and capacity of its sewer conveyance system. The existing 24-inch force main was constructed in 1975, is nearing the end of its reliable service life, and has limited capacity to convey peak wet weather flows from the City. In addition, the existing force main represents a weak link in the critical sewer conveyance system, and this second force main will provide redundancy and increase reliability for the City's sewer conveyance system. The City is requesting funding for the project from the State Water Resources Control Board, State Revolving Fund Loan Program.
Contact Information
Name
Darrin Jenkins
Agency Name
City of Rohnert Park
Contact Types
Lead/Public Agency
Phone
Location
Cities
Rohnert Park
Counties
Sonoma
Cross Streets
Wilfred Avenue / Stony Point / Business Park Drive
Zip
94928
Total Acres
3.5 miles
Parcel #
Various
State Highways
101 and 116
Railways
Northwestern Pacific, RR
Airports
N/A
Waterways
Laguna de Santa Rosa, Bellevue / Wilfred Flood Control Channel
Notice of Determination
Approving Agency
City of Rohnert Park
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA