Carbon Canyon Dam Sewer Pipeline Project

5 Documents in Project

Summary

SCH Number
2004091119
Lead Agency
Orange County Sanitation District
Document Title
Carbon Canyon Dam Sewer Pipeline Project
Document Type
NOD - Notice of Determination
Received
Posted
5/31/2005
Present Land Use
Present land use at the project site is open space. The project area is zoned as Open Space (OS) within the Carbon Canyon Specific Plan area, Suburban Residential Communities (1B) within the unincorporated Orange County area, and Single Family Residential (SF1-1) within the City of Brea.
Document Description
The project would construct a new 5,145-foot gravity flow sewer pipeline in the City of Brea. The 30-inch pipeline would begin at the existing Carbon Canyon Pump Station in Carbon Canyon Regional Park and would tie into the existing Carbon Canyon Interceptor at the intersection of Rose and Vesuvius Drive. A pipe size up to 36-inches may be required to accommodate flows, but would not increase capacity. It is anticipated that construction would start early 2006 and would likely extend to the early part of 2007. The project includes the Expanded Service Area Option, which would serve approximately 3,675 acres of unincorporated Los Angeles County and the City of Chino Hills in San Bernardino County that are adjacent to and naturally drain into the Orange County Sanitation District's service area through the City of Brea.

Contact Information

Name
Jim Herberg
Agency Name
Orange County Sanitation District
Contact Types
Lead/Public Agency

Location

Cities
Brea
Counties
Orange
Cross Streets
Carbon Canyon Road / Valencia Avenue / Rose Drive
Parcel #
322-031-04
State Highways
57
Railways
N/A
Airports
N/A
Waterways
N/A
Township
3S
Range
9W
Section
8,17
Base
S

Notice of Determination

Approving Agency
Orange County Sanitation District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print