Oro Grande Wash Percolation Facilties - Pilot Basin #2 Project

2 Documents in Project

Summary

SCH Number
2004031147
Lead Agency
Victor Valley Water District
Document Title
Oro Grande Wash Percolation Facilties - Pilot Basin #2 Project
Document Type
NOD - Notice of Determination
Received
Posted
5/17/2004
Present Land Use
Land uses vary from residential to floodway
Document Description
Install approximately 1,000 lineal feet of transmission pipeline. Construct two recharge basins containing encompassing about two acres of area. Other facilities to be installed as part of the proposed project include basin inlets, flow meters, related electrical equipment, etc. Once all facilities are operational, the District proposes to recharge up to 1,000 acre feet of potable water from the water distribution system over the next 6-12 months. An existing monitoring well, and other monitoring activities, will be used to evaluate the effectiveness of the recharge program.

Contact Information

Name
Randy Hill
Agency Name
Victor Valley Water District
Contact Types
Lead/Public Agency

Location

Cities
Victorville
Counties
San Bernardino
Cross Streets
Yates Road and Cypress Avenue
Total Acres
2.0
State Highways
I-15
Waterways
Oro Grande Wash
Township
5 N
Range
4 W
Section
29
Base
SBM
Other Information
The proposed Pilot Basin #2 Project will be installed on two (2) acres within 64 acres of recently acquired VVWD land located east of the Interstate 15 Freeway and south of Yates Road. The site is located south of the Green Tree golf course and Yates road, amidst residential and vacant lands, in the City of Victorville. This site is situated within the northeast 1/4 of Section 29, T5N, R4W SBM.

Notice of Determination

Approving Agency
Victor Valley Water District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print