Modesto Irrigation District (MID) Claribel/Minniear Project

3 Documents in Project

Summary

SCH Number
2003062147
Lead Agency
Modesto Irrigation District
Document Title
Modesto Irrigation District (MID) Claribel/Minniear Project
Document Type
NOD - Notice of Determination
Received
Posted
7/6/2004
Present Land Use
Various, including road and canal right of way, current utility right of way, agricultural, residential
Document Description
On August 12, 2003, a Mitigated Negative Declaration was adopted for the Claribel/Minniear Project, which involves building two substations and 5 miles of new transmission line (approximately 65 poles( on the north side of Modesto, Califronia. The Project was approved on that date and a Notice of Determination was duly filed. Since that time, MID has determined that in order to cross Hetch Hetchy lines along the approved route, two poles will have to be 15 feet taller than the maximum structure heights of 60-75 feet that were described in the initial study. The two poles will be placed adjacent to the Hetch Hetchy transmission lines, a steel lattice tower system over 110 feet in height.

Contact Information

Name
Ed Jeffers
Agency Name
Modesto Irrigation District
Contact Types
Lead/Public Agency

Location

Cities
Modesto, Riverbank
Counties
Stanislaus
Cross Streets
Roselle Ave. Claribel, Oakdale and Clause Roads
Railways
AT&SF RR
Waterways
MID Lateral #6 and MID Main Canal

Notice of Determination

Approving Agency
Modesto Irrigation District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.