North Green Valley Interceptor Sewer Upgrade Project

3 Documents in Project

Summary

SCH Number
2003021068
Lead Agency
Leucadia County Water District
Document Title
North Green Valley Interceptor Sewer Upgrade Project
Document Type
NOD - Notice of Determination
Received
Posted
4/18/2003
Present Land Use
Open space, community commercial and residential low-medium density.
Document Description
North Green Valley Interceptor consists of two parallel pipelines located in or adjacent to El Camino Real. The first pipeline was built in 1966 and the second was constructed in the early 1980s. In order to address issues elated to deficient capacity in the older pipeline, LCWD is proposing to divert some of the flows in the existing pipeline into a newer pipeline which can accommodate these flows. A total of 300 feet of new pipeline and one new manhole would be constructed to connect the two pipelines. In addition, LCWD proposes to repair 2,150 feet of pipeline that has been damaged or cracked as a result of tree root and groundwater infiltration, conduct point repairs at five locations, and rehabilitate 23 manholes.

Contact Information

Name
Mike Bardin
Agency Name
Leucadia County Water District
Contact Types
Lead/Public Agency

Location

Cities
Carlsbad
Counties
San Diego
Cross Streets
El Camino Real between Olivehain & La Costa Ave.
Zip
92009
Total Acres
11.2
Parcel #
N/A (multiple)
State Highways
S-11
Schools
El Camino Creek Elementary School
Waterways
Encinitas Creek, San Marcos Creek, Batiquitos Lagoon
Township
13&14S
Range
4W
Section
35,14,
Other Information
Section: 11 Base: USGS7.5/ENCINITAS

Notice of Determination

Approving Agency
Leucadia County Water District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print