Impacted Soil Removal Workplan for Site Improvements at the Former Willows Manufactured Gas Plant
3 Documents in Project
Summary
SCH Number
2002062067
Lead Agency
California Department of Toxic Substances Control
(DTSC)
Document Title
Impacted Soil Removal Workplan for Site Improvements at the Former Willows Manufactured Gas Plant
Document Type
NOD - Notice of Determination
Received
Posted
10/21/2015
Present Land Use
Industrial
Document Description
The project is the approval of an impacted soil removal workplan by DTSC that would authorize activities related to the mitigation of Polycyclic Aromatic Hydrocarbon, arsenic, and lead found in soil at the Former Willows Manufactured Gas Plant. The contaminated soil is present beneath a warehouse that is scheduled for demolition. Activities to be conducted pursuant to the approved impacted soil removal workplan include: excavate approximately 200 cy of impacted soil and transport it off-site for disposal at a permitted facility; import approximately 200 cy of clean fill; and repair any damage to existing cover currently surrounding the warehouse if needed after soil removal.
The existing land use covenant restricting the site to industrial/commercial use and the operation and maintenance agreement with the PG&E Company will remain in place.
Contact Information
Name
Duane White
Agency Name
Department of Toxic Substances Control
Contact Types
Lead/Public Agency
Phone
Location
Cities
Willows
Counties
Glenn
Cross Streets
Eastwood Street
Total Acres
1.84
Parcel #
3-081-01
State Highways
162
Railways
Southern
Airports
Willows Airport
Waterways
Glenn-Colusa Canal
Township
19N
Range
3W
Section
10
Notice of Determination
Approving Agency
Department of Toxic Substance Control
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.