Welch et al

2 Documents in Project

Summary

SCH Number
2001111019
Lead Agency
San Benito County
Document Title
Welch et al
Document Type
NOD - Notice of Determination
Received
Posted
12/18/2003
Document Description
The project involves the construction of a third of a mile long, 22-foot wide, 8-foot deep buried dike that would be covered over by 2 feet of soil. The dike would create a defined riparian buffer of 150 to 250 feet from the current channel for the Tres Pinos Creek. Construction will involve digging a trench 8 feet deep and 10 feet wide at the base. The trench would be filled with clean riprap with a minimum of 2-foot soil cover and there would be approximately 4,000 cubic yards of fill involved in the construction the berm. Following construction, plantings of willows and other native vegetation would occur on the west face and approximately 130,000 cubic yards of agricultural fill would be placed on the east side of the berm over a period of 10 years. Construction is proposed to be phase over 2 to 4 years.

Contact Information

Name
Susan Heiser
Agency Name
San Benito County
Contact Types
Lead/Public Agency

Location

Counties
San Benito
Cross Streets
Highway 25 and Bolado
Zip
95023
Total Acres
30+
Parcel #
22-25-08,-09,-10
State Highways
25
Waterways
Tres Pinos River
Other Location Info
814-976 Bolado Rd.

Notice of Determination

Approving Agency
San Benito County Planning Director
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print