New Elementary School Site No. 4 - Expansion Project (Former Dewey Alternative School Site)

4 Documents in Project

Summary

SCH Number
2001092029
Lead Agency
Oakland Unified School District
Document Title
New Elementary School Site No. 4 - Expansion Project (Former Dewey Alternative School Site)
Document Type
NOD - Notice of Determination
Received
Posted
6/7/2002
Present Land Use
Public school, residential, commercial; S-15 and R-30/Neighborhood Center Mixed Use and Mixed Housing Type
Document Description
The proposed project would implement Phase II of the Oakland Unified School District's plan to expand the capacity of the ASCEND School to accommodate 380 students. (Phase I of this project was determined by the School District to be exempt from CEQA.) The project would expand the existing 0.73-acre site to 2.6 acres by closing a segment of 38th Avenue; and demolishing all existing structures. The project would include demolition of the existing school building, and construction of a new two-story 52,200 square foot building. The project would add a large play area and off-street parking for 97 vehicles.

Contact Information

Name
Timothy E. White
Agency Name
Oakland Unified School District
Contact Types
Lead/Public Agency

Location

Cities
Oakland
Counties
Alameda
Cross Streets
East 12th Street, between 37th and 39th Avenues
Zip
94601
Total Acres
2.6
Parcel #
033-2159-001-03, -04, -003; 033-2160-002, -003-02, -004-02, -005-02, -007-02, -015-01, -015-02,
State Highways
I-880
Schools
8 OUSD public schools
Other Information
Parcel #s Cont.: 033-2160-016 and 033-2160-017

Notice of Determination

Approving Agency
Oakland Unified School District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.