Sorrento-Miramar Curve Realignment and Second Main Track Project
6 Documents in Project
Summary
SCH Number
2001081134
Lead Agency
North County Transit District
Document Title
Sorrento-Miramar Curve Realignment and Second Main Track Project
Document Type
NOD - Notice of Determination
Received
Posted
10/21/2002
Present Land Use
Commercial
Industrial
Open Space, and Industrial Commercial Mix.
M-1A, M1-B, R-15, and A-1 (Light industrial, commercial, residential, and agriculture).
Document Description
The objective of the project is to increase reliability and reduce travel time on a segment of the existing rail corridor that currently has a single-track. The Proposed Project would do the following: 1) Realign the existing railroad track within the existing right-of-way to straighten some curves, 2) Add 3.1 miles of new second track (2.2 miles within the existing railroad right-of-way and 0.9 miles within new right-of-way), and 3) Close a 3.1-mile gap of single-tracked railroad between double-tracked railroad sections at both ends of the project.
Contact Information
Name
Kate Stonelake
Agency Name
North County Transit District
Contact Types
Lead/Public Agency
Phone
Location
Cities
San Diego
Counties
San Diego
Cross Streets
Interstate-805, Miramar Road
Zip
92121
Total Acres
43.85
State Highways
SR 56, I-5 and 805
Railways
LOSSAN Rail
Schools
La Jolla Day School, UCSD
Waterways
Pacific Ocean, Los Penasquitos Lagoon, Carroll Creek, Soledad Creek
Township
15S
Range
3W
Section
5,8-10
Notice of Determination
Approving Agency
North San Diego County Transit
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.