Western Midway Sunset Cogeneration Company Project

2 Documents in Project

Summary

SCH Number
2001029020
Lead Agency
California Energy Commission
Document Title
Western Midway Sunset Cogeneration Company Project
Document Type
NOD - Notice of Determination
Received
Posted
2/27/2001
Document Description
The Western MSCC Power Project will be a nominal 500 megawatt, natural gas-fired, combined cycle, with two combustion turbine generators and, two heat recovery steam generators, which will supply one steam turbine generator. The Western MSCC plant will be located adjacent to an existing 225 MW Midway Sunset Congeneration power plant.

Contact Information

Name
Jack Caswell
Agency Name
California Energy Commission
Contact Types
Lead/Public Agency

Location

Counties
Kern
Other Location Info
Fellows, California

Notice of Determination

Approving Agency
California Energy Commission
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.