Clear Lake Basin 2000 Phase II US EPA Region IX (NEPA)

2 Documents in Project

Summary

SCH Number
1999102005
Lead Agency
Lake County Sanitation District
Document Title
Clear Lake Basin 2000 Phase II US EPA Region IX (NEPA)
Document Type
NOD - Notice of Determination
Received
Posted
1/10/2000
Document Description
The proposed action addressed by this Environmental Assessment / Initial Study is the second project developed to meet the objectives of the Clear Lake Basin 2000 Clean Water Initiative, a long-range program for environmental protection and optimization of wastewater generated within the Clear Lake Basin. The proposed action would integrate regional water reuse capabilities by providing a pipeline connection between LACOSAN's Northwest RWTP and Southeast RWTP. Additionaly, the proposed action would provide additional reuse opportunities through the construction of wetlands along the pipeline route. The proposed action would include the following components: --Construction of a Wetlands Flow Control Facility at the Northwest RWTP to provide a usable storage capacity of up to 2,200 acre-feet. --Construction of a 16-inch, 24-mile wetlands interconnection pipeline and related facilities between the Northwest RWTP and the Southeast RWTP. This includes implementation of a three mile segment between the Clearlake Oaks WWTP and the Southeast RWTP by Clearlake Oaks County Water District. Two pump stations would also be constructed. --Construction of up to 11 constructed and / or enhanced wetlands at LACOSAN facilities. These components would be integrated with existing facilities, including the Northwest RWTP, the Clearlake Oaks WWTP, the Southeast RWTP, and the Southeast Geysers Effluent Pipeline, to provide integrated recycled effluent use within the Clear Lake Basin. All facilities under the proposed action would be designed as a "closed system" for zero discharge of applied recycled water, and would comply with Waste Discharge Requirements established by the Central Regional Water Quality Control Board.

Contact Information

Name
Mark Dellinger
Agency Name
Lake County Sanitation District
Contact Types
Lead/Public Agency

Location

Cities
Lucerne, Nice, Paradise, Orchard, Clearlake Oaks, Paradise
Counties
Lake
Cross Streets
various
Total Acres
265
Parcel #
various
State Highways
20,29
Waterways
Clear Lake and Tributaries

Notice of Determination

Approving Agency
Lake County Sanitation District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.