Tule River Basin Investigation / Success Lake Capacity Expansion NOD

7 Documents in Project

Summary

SCH Number
1999044004
Lead Agency
Lower Tule River Irrigation District
Document Title
Tule River Basin Investigation / Success Lake Capacity Expansion NOD
Document Type
NOD - Notice of Determination
Received
Posted
3/5/2021
Present Land Use
Water storage reservoir (Success Lake)
Document Description
This document was prepared as a Supplemental EIR to the 1999 FEIR/FEIS for the Project. The Project consists of constructing a 10 foot-high concrete ogee weir across the Lake Success spillway, which would raise the maximum gross pool elevation from 655.1 feet to 665.1 feet. This would add approximately 28,000 acre-feet ofjoint-use flood control and irrigation water storage space in the reservoir, increasing storage capacity from 82,300 to 110,300 acre- feet. The reservoir surface area would increase from 2,400 to 3,120 acres. As part of the Project, Southern CA Edison will replace/raise transmission towers over the lake and will replace/relocate some distribution lines around the lake.

Contact Information

Name
Eric Limas
Agency Name
Lower Tule River Irrigation District
Contact Types
Lead/Public Agency

Name
Agency Name
Lower Tule River Irrigation District
Contact Types
Project Applicant

Location

Cities
Porterville
Counties
Tulare
Cross Streets
HWY 190 / Headquarters Drive
Zip
93257
Total Acres
Lake surface+720
Parcel #
various
State Highways
190
Railways
N/A
Airports
N/A
Schools
N/A
Waterways
Tule River and Lake Success

Notice of Determination

Approving Agency
Lower Tule River Irrigation District
Approving Agency Role
Lead Agency
Approved On
County Clerk
Tulare
Final Environmental Document Available at
357 E. Olive Avenue, Tipton, CA 93272

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613. For more information, please visit OPR’s Accessibility Site.