Zone Change (MCAS Tustin Specific Plan Amendment)

28 Documents in Project

Summary

SCH Number
1994071005
Lead Agency
City of Tustin
Document Title
Zone Change (MCAS Tustin Specific Plan Amendment)
Document Type
NOD - Notice of Determination
Received
Posted
7/26/2007
Present Land Use
Vacant and dedicated for a roadway.
Document Description
The Operator proposes to alter the streambed and bank by developing ~820 acres of land in four phases within a portion of the former MCAS Tustin military facility. Approximately 185 acres of the site is approved by the City of Tustin to include 2,105 residential units. Approximately 234 acrse of the site is approved for 6.7 million square feet of commercial development, including employment-oriented uses and a 16-acre neighborhood shopping center to serve local residents. In addition, the project would include approximately 170 acres of public and private parks and open space, as well as a new high school and a new elementary school, and infrastructure improvements.

Contact Information

Name
Erinn Wilson
Agency Name
Dept. of Fish and Game
Contact Types
Lead/Public Agency

Location

Cities
Tustin
Counties
Orange
Cross Streets
Tustin Ranch Road and Walnut Avenue
State Highways
SR 55
Railways
OCTA, SCRRA
Waterways
OCFCD Channel
Other Location Info
Tustin Ranch Road between Walnut Avenue and the future alignment of Valencia North Loop Road.

Notice of Determination

Approving Agency
DFG
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No