SCH Number 2024010699
Project Info
- Title
- Conditional Use Permit No. 23-013/Stroud Energy Storage Project
- Description
- The applicant (Stroud ESS, LLC) proposes to construct and operate a battery energy storage facility capable of delivering up to 250 megawatts (MW) of energy storage capacity and associated ancillary services into the California electric grid. The proposed project will be comprised of battery modules installed in racks housed in outdoor battery energy storage system (BESS) enclosures, associated equipment, a project substation, and a generation tie-line (gen-tie) to connect the proposed project to the adjacent Antelope Substation.
2 documents in project