SCH Number 2022110127
Project Info
- Title
- Gilroy Data Center
- Description
- Amazon Data Services (the applicant) proposes to build a data center (the project) at an undeveloped parcel located at the southeast end of Arroyo Circle in the City of Gilroy (the City). The project would support two data center buildings with a maximum electrical demand of 49 MW each and one security building totaling approximately 438,500 square feet. The project would also include the installation of two Battery Energy Storage Systems (BESS) to store energy in case of a power failure, a new electrical substation, and 27 backup generators, which include 25 Tier-2 emergency diesel-fired generators capable of supporting the maximum demand of 49 MW required for full operation of the Phase I servers, a 600 kW emergency generator for safety systems in the Phase I building and a 175kW backup generator for the security building (See attached for additional details).
2 documents in project