- Little Avenue Force Main and Lift Station Improvements
- Description
- The Proposed Project is the replacement of approximately 2,872 linear feet of 4-inch and 6-inch forced main wastewater pipeline with a 10-inch pipeline, one lift station, relocation of one control box, and the installation of a backup generator. The Project area starts at the Oregon/Little Avenue intersection travels east for 2,872 feet and terminates at the existing connection located in the City's old wastewater facility. The Project will abandon in place portions of the pipeline while removing other portions. Most of the construction will occur within the existing Little Avenue ROW, except for approximately 280 feet that will occur within the City's utility easement on private land and the section crossing under a BWD irrigation canal. The replacement of the pipeline under the irrigation canal will be completed using horizontal direction drilling