SCH Number 2017092028
Project Info
- Title
- RD 404 Van Buskirk Levee Cutoff Wall
- Description
- The project is the improvement of approx 1,100 lf of an earthen levee along the north bank of French Camp Slough. The project proposes the installation of a continuous cutoff wall in the center of the levee, either vinyl sheets or a soil-bentonite mix, to a depth of approx 30 ft. Upon installation of the cutoff wall, the installation area would be backfilled and an all-weather road installed on the levee top.
3 documents in project