SCH Number 2017051003


Project Info

Title
TL 695 and TL 6971 Reconductor Project
Description
San Diego Gas & Electric proposes to reinforce the electric transmission system in southern Orange County and Marine Corps Base Camp Pendleton by replacing the conductor (electrical wire) on a 10.24 mi long section of TL 695 and TL 6971 between the Talega, Japanese Mesa, and Basilone Substations. The proposed project would involve reconductoring segments of TL 695 and TL 6971, replacing existing wood pole structures with new steel pole structures, and installing a new underground power line.
Download CSV New Search

 

3 documents in project

Type Lead/Public Agency Received Title
California Public Utilities Commission (CPUC) TL 695 and TL 6971 Reconductor Project
California Public Utilities Commission (CPUC) TL 695 and TL 6971 Reconductor Project
California Public Utilities Commission (CPUC) TL 695 and TL 6971 Reconductor Project